Conveyor Belt
Conveyor Belt Project
Part 1
Project Description
The new computer-controlled conveyor belt is an exciting project that moves and positions items on the conveyor belt within < J millimeter. The project will produce a new system for future installations, and for replacement of those in the field, at a low cost. The computer-controlled conveyor belt has the potential to be a critical unit in 30 percent of the systems installed in factories. The new system is also easier to update with future technologies. The Project Priority Matrix for the Conveyor Belt Project (CBP) is:

Constrain Enhance Accept

Assignment
Develop the WBS outline using the software available to you.

TABLE A2.6
Conveyor Belt Project; WBS

Conveyor Belt Project

Hardware

Hardware specifications Hardware design Hardware documentation Prototypes Order circuit boards Assemble preproduction models Kernel specifications Drivers Disk drivers Serial I/O drivers Memory management Operating system documentation NetWork interface Utilities specifications Routine utilities Complex utilities Utilities documentation Shell Architectural decisions Integration first phase System hard/software test Project documentation Integration acceptance testing

Question
Does this information (WBS) allow you to define any milestones of the project? Why why not? What are they? Remember: Save your file for future exercises!

or

Use your file from Part I and the information provided below to complete this exercise. (See Table A2.7.) 1. Each work package will represent an activity. 2. The project begins January 4, 2010. 3. The following holidays are observed: January I, Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26. 4. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off. 5. The project team work eight-hour