Week 5
Week 5 Case Study
Operation Management
Abel Edouard
Keller Graduate School of Management
GM583
November 28, 2010
Walter Mamak

Managing Hard Rock 's Rockfest
Identify the critical path and its activities for Rockfest. How long does the project take?
The critical path is A-D-E-F-G-O
A Finalize and building contracts. Activity time 7 Early start 0 Early finish 7 Late start 0 Late Finish 7 Slack 0
D Design promotional Web site. Activity Time 5 Early Start 10 Early Finish 15 Late Start 10 Late Finish 15 Slack 0
E Set TV deal. Activity time 6 Early start 15 Early finish 21 Late start 15 Late Finish 21 Slack 0
F Hire director. Activity time 4 Early start 21 Early finish 25 Late start 21 Late Finish 25 Slack 0
G Plan for TV camera placement. Activity time 2 Early Start 25 Early finish 27 Late start 25 Late Finish 27 Slack 0
O Passes and stage credentials. Activity time 7 Early Start 27 Early finish 34 Late start 27 Late Finish 34 Slack 0
With the information provided, the project will take 34 weeks to complete. The critical path is in red color.
Which activities have a slack time of 8 weeks or more?
With the information provided and the dependencies that I created based on my assumptions, these are the tasks that have more than 8wk slack time:
Task P (finalize sponsors).
Since there are a lot of activities that are not linked (successors), it is somewhat difficult to predict additional activities with > 8wk slack time.
Identify five major challenges a project manager faces in events such as this one.
Some major challenges a project manager faces would be planning systematically all aspects of the project, and solicit active involvement from all functional areas involved, in order to obtain and maintain a realistic plan that satisfies their commitment. a. Rain delays in the construction.
b. Government agency permits for construction delays. c. Telecommuting. d. Missing tools for the construction. e.Unstrict management. They would need to



References: Heizer, J. and B. Render 9th ed. (2009) Operation Management. Prentice Hall Retrieved November 28, 2010. Managing Hard Rock 's Rockfest video (2009), Retrieved November 28, 2010.

You May Also Find These Documents Helpful

  • Powerful Essays

    PROJ 592

    • 2367 Words
    • 10 Pages

    An Earned Value analysis reflected that the project is currently behind schedule. The schedule variance (SV) indicated a negative $565,226.34 and the scheduled performance index showed as .69. When SV is a negative number and SPI less than one, this indicates the project is behind schedule. After calculating the CPI/SPI value (1/.69= 1.45), any values above 1.3 should be investigated immediately, because those numbers are much too good to be true. In addition based on the Work Breakdown Structure the total duration was 6 days behind schedule. The new completion date in the WBS also indicates that the schedule completion date currently is 10days behind schedule.…

    • 2367 Words
    • 10 Pages
    Powerful Essays
  • Good Essays

    Hrm/531 Week 4

    • 643 Words
    • 3 Pages

    Schedule Variance of E – We have a huge –ve SV of $16000 but a +ve CV. Although we are in budget, we are not getting work done well. The best way is to either improve the scheduling because no manager can create a poor schedule or increased motivation for the workers to get more work done. We can also improve the scenario by efficient scheduling of existing tools required to complete the task among the workers so that tools do not remain idle for a long period of…

    • 643 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Unit 421 Unit 7

    • 686 Words
    • 3 Pages

    The resource allocation for each activity for each week and the total weekly resource assignments are show…

    • 686 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Managerial Statement: The expected duration of the project is 31 working days. Critical Activities are I, J, K, L, and M.…

    • 678 Words
    • 3 Pages
    Satisfactory Essays
  • Better Essays

    JGT2 ALL

    • 10845 Words
    • 44 Pages

    produces 6 workboots in one hour with a 40 hour work week making this the most appropriate layout for the…

    • 10845 Words
    • 44 Pages
    Better Essays
  • Powerful Essays

    Pm592 Course Project 2

    • 3890 Words
    • 16 Pages

    After entering the data and setting the project to 40% completion, we noticed that the project is behind schedule. This was apparent by the Schedule Variance and the SPI (Schedule Performance Index). The Schedule Variance for the project is ($570,977.84) with a Schedule Variance Percentage of -35%. We also noticed that…

    • 3890 Words
    • 16 Pages
    Powerful Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    3. The activity that has the greatest amount of slack is Detailed Marketing Plan, of 179 days.…

    • 402 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    Decide how much time you will need to spend each week to achieve your task on time.…

    • 1723 Words
    • 7 Pages
    Powerful Essays
  • Good Essays

    Pinto Pm2 Ism Ch12

    • 3225 Words
    • 23 Pages

    3. Those with the lowest activity identification number (e.g., those that start earliest in the WBS)…

    • 3225 Words
    • 23 Pages
    Good Essays
  • Powerful Essays

    Blue Zuma

    • 1757 Words
    • 8 Pages

    The ARC Company specializes in developing and selling a wide range of high quality scooters. Sales representatives report that there is a growing demand for racing scooters. ARC’s president, Robin Lane, is excited about the possibilities and predicts that one day these kinds of razor scooters will be featured in X-Game events. ARC is a small company and uses a strong matrix to optimally utilize limited manpower.…

    • 1757 Words
    • 8 Pages
    Powerful Essays
  • Good Essays

    The critical path would change to include activity 6 as well as activity 7. The overall duration of the project will remain 24 weeks.…

    • 484 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Proj Mngment

    • 345 Words
    • 2 Pages

    “The critical path is the path (from start to finish) that joins all activities with zero slack” (QSO 640 Module 7)…

    • 345 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    3. What is (are) the critical path(s) in the project? What is the level of risk in completing tasks on the critical path(s)? Explain.…

    • 613 Words
    • 3 Pages
    Good Essays
  • Better Essays

    The last section of Table 1 highlights the slack time available for any given task (A-J). In order for the slack time to be calculated for each task the project manager must subtract the LF from the EF in each task. “All of the jobs on the critical path, by…

    • 1185 Words
    • 5 Pages
    Better Essays
  • Best Essays

    Evans, James R. and William M. Lindsay. The Management and Control of Quality. Thomas South-…

    • 1969 Words
    • 8 Pages
    Best Essays